Phased Outdoor Remodel Roadmap (2025) — 6‑, 12‑, 18‑Month Plans & Financing

Updated August 2025 — San Diego County

Luke W., Owner of INSTALL-IT-DIRECT

Written by:
Luke W., Founder & Owner of INSTALL-IT-DIRECT
Luxury Landscape Design & Build Expert • 16+ Years in San Diego

Chris MacMillan, General Manager

Reviewed by:
Chris MacMillan, General Manager
ICPI Certified • CA CSLB License #947643
Last reviewed: August 2025 · About our process
6,000+ 5‑star reviews since 2009 • Fully licensed & insured in California

Want a resort‑level backyard but need to spread costs—or your HOA/permits require staging? This roadmap shows how to design once and build in phases (6, 12, and 18 months) without redoing work. We cover sequence, cash‑flow and financing options, permit/HOA strategy, and lead‑time planning—so you get the full vision with zero “tear‑out tax.”

Do‑This‑First — Compliance Quick‑Start (San Diego)

  • Confirm jurisdiction & overlays: Use the City’s ZAPP zoning map or Permit Finder (City) and the County’s Zoning & Property Info map (unincorporated) to identify Coastal Overlay, steep slopes/ESL, flood, historic, and ROW constraints.
  • Pick a permit strategy up front: Submit one master plan (grading, drainage, utilities, structures) and pull phase‑appropriate sub‑permits (Simple MEP, ROW, grading) tied to your 6/12/18‑month schedule.
  • Stormwater first: Complete the City’s DS‑560 Stormwater Applicability Checklist and include drainage/BMPs on Phase‑1 plans.
  • Coastal Overlay? Plan for a separate City‑issued Coastal Development Permit (CDP) where required.
  • Historic screen (45‑year rule): If any structure on site is ≥45 years old or in a district, follow IB‑580/IB‑581 before pulling even Simple permits.

TL;DR — Phased Remodel That Doesn’t Cost You Twice

  • Design once, build in phases: full master plan with utilities, grading, drainage, and sleeves mapped on day one.
  • Phase smart: do undergrounds, drainage, retaining, utilities, and base hardscape first; verticals & finishes later.
  • Control cost: avoid re‑mobilization waste with correct order of operations; pre‑buy long‑lead items to lock pricing.
  • Cash‑flow: spread investment over 6 / 12 / 18 months; use budget tiers ($100k / $250k / $500k+) to scope per phase.
  • Permits/HOA: one master plan, then pull sub‑permits as needed (ROW, electrical, grading, kitchen/gas) to match phase timing.

6‑, 12‑, and 18‑Month Phased Plans (Examples)

Phasing Scenarios — What Happens When (and Why)
Plan Phase & Window Core Scope Dependencies Typical % of Total
6‑Month (Single‑Season)
For tight HOA deadlines & new builds
Phase 1 (Weeks 1–8) Grading, drainage, sleeves, utilities (gas/electrical/data), walls/retaining, driveway base + pavers, patios (core), stub‑outs for kitchen/pergola, rough lighting conduits. Master plan; approvals; material orders placed at Day 0. ~65–75%
Phase 2 (Weeks 9–20) Pergola install, outdoor kitchen finish (appliances, gas), lighting fixtures & transformer, turf/putting green, planting/irrigation, controls & scenes. Phase‑1 rough‑ins complete; inspections as required. ~25–35%
12‑Month (Two‑Phase)
Most popular for full yard overhauls
Phase 1 (Months 0–4) All sitework + hardscape shells: walls, drainage, drive/patios/walks, low‑voltage sleeves, gas/electrical stubs, kitchen/pergola footings. ROW/permits cleared; long‑lead items ordered at Day 0. ~60–70%
Phase 2 (Months 5–12) Pergola + kitchen finish, lighting fixtures & programming, turf/greens, softscape, water features, final controls. Phase‑1 shells/roughed utilities in‑place. ~30–40%
Optional “Phase 0” (Month −1): demo/haul, temporary erosion control, temporary irrigation, and pre‑ordering long‑lead materials (pergola, porcelain, appliances, gate operator).
18‑Month (Three‑Phase)
For premium estates & cash‑flow pacing
Phase 1 (Months 0–6) Grading, walls/retaining, drainage, driveway & motor‑court base/pavers, primary patios, sleeves & stubs everywhere. Master plan & permits; long‑lead orders placed. ~45–55%
Phase 2 (Months 7–12) Pergola(s), outdoor kitchen rough & finishes, fire features, equipment pads, low‑voltage wiring pull, transformer set, initial scenes. Phase‑1 sleeves/bases complete. ~25–35%
Phase 3 (Months 13–18) Turf/putting greens, planting/irrigation, lighting finishes, controls integration, punch list & maintenance plan. Earlier phases inspected & powered. ~15–25%
Seasonal tip: schedule earthwork in dry season; install plantings toward cooler months for establishment.

Cash‑Flow & Budget Tiers (How to Phase Without Overpaying)

Sample Allocation by Budget Tier (Total Program)
Tier (see Budget Guide) Phase 1 (Shells/Undergrounds) Phase 2 (Verticals/Finishes) Phase 3 (Landscape/Lighting Finish)
$100k Program ~60–70% ~30–40% Included in Ph. 2 or 5–10%
$250k Program ~55–65% ~25–35% ~10–15%
$500k+ Program ~45–55% ~35–45% ~10–15%
Phasing adds small remobilization costs; a master plan reduces these. We design sleeves/stubs to avoid opening finished work later.

Financing Playbook (Pair Cash‑Flow with Phasing)

Common Options — Pros & Considerations
Option Why Use It Considerations
HELOC / Home Equity Lower rates; interest‑only during draw; perfect for multi‑phase schedules. Variable rates; closing timelines; consult your lender/CPA.
Unsecured Project Loan Fast approvals; no lien; useful for smaller phases/adders. Higher rates; shorter terms.
Cash‑Out Refi Single payment; may lower total monthly if rates cooperate. Closing costs; rate risk; longer lead time.
Manufacturer Promos (e.g., pergola, appliances) 0%/deferred promos; align with Phase‑2/3 finish items. Promo windows; approvals/product limits.
We’re not your financial advisor—compare APRs, fees, and terms. We’ll time invoices to match draws and promos where possible.

Permits, HOA & ROW Strategy (San Diego)


Build Sequence (No Re‑Work, No Tear‑Out)

Order of operations we use on phased builds:

  1. Demo/haul, rough grading, walls/retaining, drainage design & stubs.
  2. Utilities: gas/electrical/data sleeves & conduits to every future zone (schedule concealment inspections before cover).
  3. Bases & hardscape shells (drive/patios/walks) with embedded sleeves.
  4. Vertical elements: pergolas, kitchen frames, fire features (rough).
  5. Finishes: appliances, lighting fixtures & controls, caps/veneers.
  6. Landscape/turf/putting greens, irrigation, fine grading.
  7. Commissioning: lighting scenes, equipment start‑up, client handoff.
Safety & compliance: Call 811 before trenching; Simple MEP permits require inspections prior to concealing work.

Materials & Lead‑Times (Order at “Phase 0”)

  • Louvered pergolas & gates: design/fabrication can be the pacing item; order at master‑plan approval.
  • Porcelain & specialty pavers: reserve batches to avoid dye‑lot changes; confirm drive‑rated specs for motor courts.
  • Appliances & fixtures: lock selections with loads (gas BTUs, electrical circuits/amps) so sleeves/circuits are right the first time and qualify for Simple MEP where applicable.

Typical Timeline (Concept → Completion)

  • Weeks 0–2: site measure, concept, budgets, Phase‑0 ordering list; complete City DS‑560 stormwater checklist.
  • Weeks 3–6: permit/HOA submittals as needed; earthwork scheduling.
  • Months 2–4: Phase 1 build (shells/undergrounds).
  • Months 5–12/18: Phase 2–3 finishes as funding/lead‑times align.

Common Pitfalls (and How We Avoid Them)

  • No sleeves / stubs: forces cutting finished work—our master plan prevents this.
  • Out‑of‑order work: placing pergola footings after pavers = rework. We pour anchors first.
  • Underpowered kitchens/lighting: we size gas BTUs & electrical capacity early.
  • Ignoring stormwater: we grade for on‑site solutions so later phases pass inspection (City ties grading to DS‑560 and drainage submittals).
  • Unpermitted ROW/apron work: driveway/apron/curb in public right‑of‑way requires separate ROW & traffic permits; private encroachments may need an EMRA.
  • Historic routing surprise (≥45 years): we run IB‑580/581 screening up front to keep Simple permits from being delayed.

Quote Comparison Checklist (Phased Projects)

  • Full master plan (grading, drainage, utilities, lighting, planting).
  • Phase map with clear inclusions/exclusions and dependencies.
  • Sleeve & conduit schedule with locations, sizes, and spares.
  • Permit path per phase (ROW, electrical, gas, grading, walls, pergola).
  • Selections (pavers/porcelain, pergola, appliances, fixtures) with lead‑time notes.
  • Line‑item budgets by phase + allowances for long‑lead changes.
  • Warranties & service and a maintenance/seasonal tuning plan.

Serving San Diego County: Rancho Santa Fe, Fairbanks Ranch, La Jolla, Del Mar, Carmel Valley, Encinitas, Carlsbad, Poway, Harmony Grove, Solana Beach, and more.


San Diego Code & Permit Addendum (2025)

Scope Permit Trigger (City of San Diego) Notes / Links
Patio Covers / Pergolas ≤300 sf may be permit‑exempt for SFD/duplex, but not in Coastal Overlay, ESL/historic/Planned Districts or where setbacks are impacted. IB‑206 · When is a Permit Required?
Retaining Walls Permit at >3 ft (measured above footing) or any wall with surcharge/liquids. IB‑220 · IB‑221 · Permit thresholds
ROW (driveway/apron/curb) ROW permit + traffic control; private encroachments may require EMRA. IB‑165 · IB‑177 · IB‑576
Electrical / Lighting Simple “No‑Plan” Electrical Permit for minor SFD installs; fixtures must meet SDMC §142.0740. Simple Electrical · SDMC §142.0740 · IB‑103 (MEP Fees)
Grading/Drainage City grading permit as required; include DS‑560 stormwater with submittal. City Grading Permit
Coastal Overlay Separate City‑issued Coastal Development Permit (CDP). CDP Procedures · Coastal Overlay Zone
County (Unincorporated) Grading permit typically at ≥200 CY or per ordinance; Dark‑Sky lighting rules apply. Sec. 87.201 Grading · County Light Pollution Code · PDS‑211
RSF Association (overlay) Art Jury approvals; strict grading & exterior lighting regulations. RSF Grading Regs · RSF Lighting Regs
Tip: avoid publishing trench/burial depths here—inspectors apply site‑specific rules. Put exact depths on your stamped plans (CEC Table 300.5/CPC), then pull Simple MEP or plan permits as applicable.

FAQs

What’s the best order to phase a full outdoor remodel?

Do undergrounds, drainage, and walls first; then hardscape shells with sleeves; then verticals (pergola, kitchen roughs); finish with appliances, lighting fixtures, turf/planting, and controls.

Will phasing cost me more overall?

Slightly—due to remobilization. A master plan with sleeves/stubs minimizes this and prevents rework that really drives cost.

Can permits and HOA approvals be phased?

Yes. We submit a master plan and pull sub‑permits by phase (ROW, gas/electrical, grading, walls, pergola). HOAs usually prefer seeing the full vision with a phasing note.

Do I need a Coastal Development Permit (CDP)?

If your property is in the City’s Coastal Overlay Zone, most development requires a City‑issued CDP with its own timeline. We’ll confirm and plan the path.

Are pergolas ≤300 sf exempt from permits?

Often for SFD/duplex, but not if you’re in Coastal Overlay, ESL/historic/Planned Districts, or if setbacks/height are affected. We verify exemption vs. building permit during planning.

Do I need a permit for a 3‑ft retaining wall?

Walls over 3 ft (measured from the bottom of footing) or any wall supporting surcharge/liquids require a permit. We design and submit accordingly.

How do you align financing with phases?

We time invoices to match draw schedules (e.g., HELOC) and manufacturer promo windows (pergolas/appliances) and place long‑lead orders at Phase 0.

How long does a phased remodel take?

Typical two‑phase programs complete within 12 months; premium estates often use a three‑phase, 18‑month plan.