Estate Utility Backbone (Gas • Electric • Data • Drainage) — The Pre‑Construction Plan That Saves $50k+ (San Diego 2025)
Updated September 2025 — San Diego County
Before you pour a patio or set a pavilion, lock the backbone—sub‑panels, gas trunk lines, data/Wi‑Fi, sleeves under hardscape, and lawful stormwater outlets. This is the plan we use to keep estate projects in Rancho Santa Fe, Fairbanks Ranch, Olivenhain/Harmony Grove, Santaluz/Crosby, Poway (Heritage/Old Coach), La Jolla/Del Mar, Carmel Valley/PHR, Encinitas, Carlsbad, and beyond on budget and inspection‑ready while avoiding the expensive tear‑outs.
Do‑This‑First — Site & Power Map (San Diego 2025)
- Main panel & sub‑panel strategy: amps available, feeder routes, sub‑panel near pavilion/kitchen to reduce voltage drop.
- Gas trunk plan: meter size/regulator, BTU totals (kitchen + heaters + fire features), shutoffs & sediment traps.
- Sleeves & conduits: under all planned hardscape; extras for future screens, speakers, lighting, EV/golf‑cart runs.
- Stormwater: channels/areas to lawful private outlets; curb/storm tie‑ins in ROW require permits/EMRA.
- Overlays & approvals: HOA/Art Jury, Coastal (CDP), ESL/steep slopes, WUI/Brush Mgmt—flag early.
TL;DR — 2025 Estate Backbone Allowances (San Diego)
- Electrical backbone (sub‑panel + trench + feeders): $6,000–$18,000
- Heater/screen circuits & controls: $3,000–$12,000
- Gas backbone (meter → kitchen/heaters/fire features): $3,000–$9,000 (+ appliance drops)
- Conduits/sleeves under hardscape (per run): $30–$65/LF
- Low‑voltage/data (Cat6/fiber, APs): $2,000–$12,000
- Drainage to lawful outlet (channels/areas/drywells): $10,000–$45,000+
- ROW/EMRA fees & inspection (if tying to curb/storm): $1,000–$3,000+
Packages (Good / Better / Best)
Package | What’s Included | Typical Installed |
---|---|---|
Good — Core Backbone | Sub‑panel + trench/feeder, gas trunk to kitchen/heater zone, 4–6 sleeves, Cat6 to TV, basic channel/area drains to private outlet. | $18k–$45k |
Better — Entertainment‑Ready | Adds heater/screen circuits, 2–3 extra sleeves, AP at pavilion, drywell(s)/infiltration, transformer pad & lighting zones. | $45k–$95k |
Best — Estate‑Wide Backbone | Second sub‑panel, EV/golf‑cart circuits, multi‑AP Wi‑Fi mesh, camera/gate conduits, advanced stormwater (2+ drywells), ROW tie‑ins (if allowed). | $95k–$185k+ |
Adders & Site Factors (What Moves the Needle)
Item | Typical Range | Notes |
---|---|---|
Panel Upgrade / New Sub‑Panel | $2,500–$6,000 / $1,800–$4,500 | Amps, breakers, location, inspection. |
Long Trench Distance | +$25–$55 per LF over base | Conduit, wire, backfill, restoration. |
Rock / Hard‑Dig / Sawcut & Patch | $1,200–$6,500 | Per segment; asphalt/drive crossings. |
Drywell / Infiltration System | $1,800–$6,500 each | Sizing per soils/inflow; access constraints. |
ROW Tie‑In (Curb/Storm) | $1,000–$3,000+ fees | ROW permit + EMRA + inspections. |
Survey / Utility Locate | $800–$2,200 | Property lines, easements, staking. |
Coastal Spec (AAMA 2605, SS hardware) | +$1,500–$6,000 | For structures within marine influence. |
Line‑Item Models (Estate Examples)
Item | Scope / Notes | Cost Range |
---|---|---|
Electrical Backbone | Sub‑panel near pavilion; trench & feeders; heater/screen circuits | $9,000–$22,000 |
Gas Backbone | Meter → kitchen/heaters; regulator; shutoffs; sediment traps | $4,000–$9,000 |
Conduits & Sleeves | 6 runs under patio for TV/A‑V, screens, future speakers/lighting | $2,000–$6,000 |
Data/Wi‑Fi | Cat6 to TV + AP at pavilion; media closet venting | $2,000–$6,000 |
Drainage | Channel/area drains; lawful private outlet (no curb tie‑in) | $10,000–$20,000 |
Permits / Plan Check | MEPs; ROW/EMRA if applicable; stormwater checklist | $2,000–$5,000 |
Total (Installed) | Backbone ready for pavilion + kitchen | $29,000–$58,000 |
Item | Scope / Notes | Cost Range |
---|---|---|
Electrical Backbone (Dual) | Main sub‑panel + secondary near outbuilding; long trench runs | $18,000–$36,000 |
Gas Backbone (Expanded) | Kitchen, heaters, fire features, future pool equipment tees | $7,000–$15,000 |
Conduits/Sleeves Grid | 12+ sleeves incl. gate/cameras, EV/golf‑cart, future lanterns | $6,000–$14,000 |
Data/Wi‑Fi Mesh | 3–4 AP mesh, fiber/copper home‑runs, rack/ventilation | $6,000–$16,000 |
Advanced Stormwater | 2+ drywells/infiltration beds; pipe network; cleanouts | $18,000–$45,000 |
ROW/EMRA & Permits | If curb/storm tie‑in; plan check/inspections | $3,000–$8,000 |
Total (Installed) | Estate‑wide backbone for multi‑phase build | $58,000–$134,000 |
Design & Specs (What Passes & Performs)
Electrical
- Voltage‑drop planning: place sub‑panel near pavilion; size feeders; dedicate circuits for heaters/screens/lighting.
- Outdoor GFCI/AFCI: plan protected circuits and weather‑resistant devices; locate transformer(s) for lighting.
- Controls: scenes for lighting; simple zones for heaters; label spare breakers for future phases.
Gas
- BTU summary: grill(s), burners, heaters, fireplaces, future pool equipment; size trunk & regulator accordingly.
- Shutoffs & traps: accessible shutoffs; sediment traps at appliances; pressure test per standard practice.
- Routing: avoid future footings/walls; sleeve crossings; bond per code.
Data & Wi‑Fi
- Hardline first: Cat6 to TV and A/V rack; AP at pavilion; consider fiber for long runs/outbuildings.
- Media closet: ventilation, power, surge protection; conduit entry points with drip loops.
- Coverage: mesh APs for 1–2+ acre lots; test and tune after landscaping.
Drainage & Stormwater
- Capture & convey: channel/area drains at thresholds; tie to lawful private outlets or on‑site infiltration/drywells.
- Cleanouts & slopes: maintain serviceability; slope hardscape away from structures; never trap water under slabs.
- ROW caution: curb/storm connections need City approvals (ROW + EMRA); otherwise keep discharge on site.
Permits & Overlays (San Diego Snapshot)
- Patio covers/pavilions: see Pergola/Patio Cover Permits.
- Outdoor kitchen gas/electrical: see Kitchen Permits (Gas/Electrical).
- Stormwater & ROW: drainage planning begins with Yard Drainage & Stormwater; curb/storm tie‑ins generally require a ROW permit/EMRA.
- Coastal/ESL: near the coast or on steep hillsides, see Coastal Development Permits & Bluff Setbacks.
- WUI/Brush Mgmt: for canyons/estates, see WUI Fire‑Smart Estates.
Sequence & Timeline (No Re‑Work)
Order we build: concept & budget → backbone map (power/gas/data/drainage) → sleeves & trenching → sub‑panel/regulator install → inspections → patio base & finishes → structures (pavilion/pergola) → kitchen rough‑ins → A/V & heaters → screens → lighting scenes → punch.
- Design & coordination: ~1–3 weeks
- Permits & HOA: ~2–8+ weeks (Coastal/WUI/HOA may extend)
- Backbone build: simple ~1–2 weeks • estate‑wide 3–6+ weeks
Common Pitfalls (and How We Avoid Them)
- No sub‑panel near the action: leads to voltage drop and circuit spaghetti. We place/size sub‑panels early.
- Missing sleeves: forces demolition to add screens/speakers later. We sleeve generously at concept.
- Heater clearance conflicts: solved with shop drawings and coordination with louvers, lights, and TV sightlines.
- Illegal stormwater tie‑ins: curb/gutter connections need ROW/EMRA. We design lawful on‑site outlets when ROW isn’t approved.
- Weak Wi‑Fi on 2 acres: we home‑run Cat6 and place outdoor APs for reliable streaming and control scenes.
Quote Comparison Checklist (Apples‑to‑Apples)
- Electrical: sub‑panel size/ampacity, feeder lengths/wire sizes, dedicated circuits (heaters/screens/lighting), transformer location.
- Gas: BTU schedule, regulator placement, shutoffs, sediment traps, pressure test.
- Conduits/Sleeves: count, diameters, routes, spare capacity for future phases.
- Data/Wi‑Fi: Cat6 home‑runs, AP count/locations, rack/ventilation, surge/UPS.
- Drainage: channels/areas, infiltration/drywells, lawful outlet notes, cleanouts.
- Permits/approvals: MEPs, ROW/EMRA (if any), HOA/Art Jury submittals, inspections included.
- Trench/restoration: sawcut/patch allowances, landscape/base restoration.
- Warranty & service: panels/gear, gas piping, drainage, seasonal system check.
Serving San Diego County: Rancho Santa Fe, Fairbanks Ranch, Olivenhain/Harmony Grove, Poway, La Jolla, Del Mar, Carmel Valley, Encinitas, Carlsbad, Solana Beach, Santaluz/The Crosby, Del Sur/4S Ranch, and more.
FAQs
How big should my sub‑panel be for heaters, screens, and lighting?
Most estates benefit from a dedicated outdoor sub‑panel sized for heaters/screens plus spare breakers for future phases—location close to the pavilion reduces voltage drop.
Where should stormwater from pavilions and patios go?
To lawful private outlets or on‑site infiltration (drywells). Curb/storm tie‑ins in the public right‑of‑way require approvals and often an EMRA—keep discharge on site if not permitted.
How many sleeves should I run under a 1,000–1,500 sf patio?
Plan at least 4–6 now (A/V, screens, future speakers/lighting, spare). It’s far cheaper to add extras before hardscape than to demo later.
Can I phase the backbone for HOA or Coastal deadlines?
Yes—install the trunk lines (power, gas, data, drainage) and sleeves first; add kitchen, heaters, screens, and finishes later under the same cohesive plan set.
Will Wi‑Fi reach across 1–2+ acres?
With hardline Cat6 to outdoor APs and a mesh design, yes. We map AP locations during concept so streaming and controls are reliable on day one.
Always verify parcel‑specific overlays, setbacks, easements, and HOA conditions. Where requirements conflict, the stricter standard governs.