Completed interlocking paver patio with a central square stone-veneer fire pit and contrasting inset field pattern. White...

One Renovation, House to Street: San Carlos Pavers

Project Snapshot

Location San Carlos, San Diego (92119)
Style Modern
Timeline 40 working days · spring 2023
Price Range $70k-$80k

– Orco Villa Express pavers: 755 sq ft (backyard patio and walkways)
– Orco Holland 4×8 pavers: 240 sq ft (front driveway and walkways)
– Additional Country Cobble Chateau pallets blended into the field on site (mixed with existing Villa Express stock)
– Field-measured paver coverage across both yards: about 2,000-2,125 sq ft total per pre-walk
– Angelus Polymeric Sand (small joints) applied to all paved areas
– Square natural-gas fire pit, about 22 sq ft surround, 18-inch fire ring, black fire glass; gas line trenched and pressure-tested before backfill
– Artificial turf panel installed flush within the backyard paver field, no seams
– Low segmental seat / retaining wall along the backyard edge
– Bark mulch (Forest Floor, non-dyed): 1,560 sq ft at 2-3 inch depth
– Concrete demo: 590 sq ft (backyard) + 130 sq ft (front)
– Second-phase addition: planting, drip irrigation, Mission Mountain decorative gravel, AZ Chocolate Patio Stone flagstone

– Drainage and conduit rough-in were completed during site prep, ahead of base and paver installation
– PVC drain risers were positioned and visible in subgrade-prep photos before base aggregate was placed
– Gas-line trenching (18 inches) and pressure-testing were completed early so the finished hardscape did not need to be reopened
– Drip irrigation valves and components were integrated into the second-phase landscaping work

– Active build window: about 8 weeks on site from early March 2023 to late April 2023, roughly 35 to 40 working days across a phased schedule
– Week 1 (March 6 onward): backyard demo, excavation, drainage and conduit rough-in, gas-line trenching and pressure test
– Weeks 2-3: backyard base preparation and paver installation, fire-pit construction, artificial turf
– Weeks 3-4: front driveway demo and Holland 4×8 paver installation
– Week 5 (early April): low-voltage lighting placement (positions confirmed with the homeowner) and first-phase punch
– Second-phase return (mid-to-late April): planting, drip irrigation, Mission Mountain decorative gravel, and AZ Chocolate Patio Stone flagstone, finishing with final check on April 28

Project Story

Overview

A San Carlos homeowner had a front yard that had been pretending for years: lawn patchy over compacted dirt, concrete walkway cracked into three long sections, driveway worn enough that the homeowners had stopped noticing. The back yard was not much better. Both ends got rebuilt as one project — not the usual patio-now, driveway-later. About 2,000 sq ft of new Orco interlocking pavers went across the backyard, driveway, and walkways, plus a square natural-gas fire pit, an artificial turf panel, drainage and low-voltage lighting. After the first hardscape phase, a client-approved second-phase scope addition brought planting, drip irrigation, Mission Mountain decorative gravel, and AZ Chocolate Patio Stone flagstone to finish the project.

The front and back yards used to be cracked concrete and patchy grass, and now they feel like one finished space. The crew was easy to work with through the weather and the extra landscaping we added at the end.

The Challenge

  • Cracked concrete across the patio, driveway, and walkways made the property feel worn and disconnected.
  • Patchy lawn, bare soil, and unfinished planting areas left both the front and back yards looking incomplete.
  • Drainage, lighting, and a fire feature all needed to land inside one continuous renovation — not three follow-up projects spread across years.

What Changed

About 2,000 sq ft of new Orco interlocking pavers, a square natural-gas fire pit, an artificial turf panel, drainage and low-voltage lighting, plus later planting, drip irrigation, decorative gravel, and flagstone replaced cracked concrete and patchy lawn across the front and back yards.
How INSTALL-IT-DIRECT Helped
Install It Direct rebuilt both ends of a San Carlos lot as one continuous renovation. About 2,000 square feet of Orco interlocking pavers replaced the cracked concrete — Villa Express in a modular bond across the back yard, Holland 4×8 in herringbone across the driveway and walkways. Different patterns, same gray color register, so the eye reads the property as one place. A square natural-gas fire pit with an 18-inch ring went in at the center of the back yard; the gas line was trenched and pressure-tested before the driveway base went down, because once the front is paved the crew is not coming back to trench across it. An artificial turf panel sits flush in the back-yard paver field — no seams. A low segmental seat wall runs along the back edge. Low-voltage path lights line the fence. A second-phase return wrapped in planting, drip irrigation, Mission Mountain decorative gravel, and AZ Chocolate Patio Stone flagstone.

Over 1,000 five-star reviews and 1,500+ San Diego homeowners served.

Design & Build

The Plan

  • About 2,000 sq ft of Orco interlocking pavers across the backyard patio, front driveway, and connecting walkways: 755 sq ft Villa Express in the backyard, 240 sq ft Holland 4×8 on the driveway and walkways, with additional Country Cobble Chateau pallets blended into the field on site

  • Square natural-gas fire pit (about 22 sq ft surround) with an 18-inch fire ring, set into the backyard paver field; gas line trenched and pressure-tested before backfill

  • Artificial turf panel set flush within the backyard paver field, no seams

  • A low segmental seat wall along the backyard edge, drainage and conduit rough-in completed during site prep, and low-voltage path lighting integrated through the hardscape plan

  • Client-approved second-phase addition brought planting, drip irrigation, Mission Mountain decorative gravel, and AZ Chocolate Patio Stone flagstone

The Build

Demo and Rough-In

Demo opened the project: concrete out of the driveway and patio, conduit and drainage rough-in, then the gas-line trench for the fire pit before any base went down.

Backyard Hardscape

The backyard paver field moved first, with crews laying Orco Villa Express units in a modular pattern, shaping the fire-pit surround, and working around rain delays on March 15 and March 21.

Driveway and Walkways

Once the backyard was substantially in place, the team replaced the front driveway and walkways with Orco Holland 4×8 pavers in a herringbone field pattern with soldier-course borders and curved edge restraints at the entry.

Turf and Lighting

Artificial turf went in after the hardscape edges were set, and the low-voltage lighting layout was placed and adjusted with the homeowner before first-phase punch work.

Second-Phase Landscaping and Closeout

A return visit, scheduled with the homeowners, wrapped in planting, drip irrigation, Mission Mountain decorative gravel, and AZ Chocolate Patio Stone flagstone. Final check April 28.

Investment

What would a similar project cost in San Diego?

Toggle components on/off to estimate your project

Pavers & Hardscape $44,500 – $51,000
Artificial Turf & Landscaping $9,500 – $11,000
Demo & Site Work $5,500 – $6,500
Drainage $4,500 – $5,000
Lighting $3,000 – $3,500
Walls & Steps $2,000 – $2,000
Fire Feature $1,000 – $1,000
Estimated Total

Frequently Asked Questions

What did this San Carlos project cost?

A project like this one — about 2,000 sq ft of pavers, a natural-gas fire pit, an artificial turf panel, drainage, low-voltage lighting, and a second-phase landscaping return — generally lands around $70,000 to $80,000 in San Diego for a comparable scope today. The homeowners' actual sold price (mid-2023) varied based on the line-item mix they selected and material substitutions during the build. Material selection, access, gas-line work, and any later scope additions can move the total up or down.

How much maintenance do pavers, turf, and gravel beds need after installation?

The pavers mainly need normal sweeping, occasional rinsing, and periodic joint-sand touchups if needed. Artificial turf benefits from brushing and debris removal, while gravel and planted beds need occasional cleanup, irrigation checks, and plant pruning. The point of this layout was lower upkeep than cracked concrete plus patchy lawn.

How long does a paver driveway, patio, and fire pit project like this take?

This project ran about 8 weeks end to end (roughly 35 to 40 working days on site, from early March to late April 2023) because it covered both the backyard and the front approach, included rain interruptions, and added a planting-and-irrigation second phase. Simpler hardscape-only projects can move faster; multi-phase projects of this size usually need extra time for utilities, deliveries, and a return visit.

Does a natural-gas fire pit involve special gas-line work?

Yes. A natural-gas fire feature requires a gas line trenched, sleeved, and pressure-tested before the hardscape goes back over the top — that work is what was done on this project, with the gas line set under the paver field before backfill so the finished surface did not need to be reopened. Permit and inspection requirements vary by exact scope and municipality; confirm with your contractor for your specific project.

What materials were used on this San Carlos driveway and patio project?

The backyard paver field is Orco Villa Express across about 755 sq ft, with additional Country Cobble Chateau pallets blended into the field on site. The front driveway and walkways are Orco Holland 4×8 across 240 sq ft in a herringbone pattern. The project also included an artificial turf panel set flush in the backyard, a square natural-gas fire pit with an 18-inch ring, low-voltage path lighting, and a low segmental seat wall. The second-phase addition brought planting, drip irrigation, Mission Mountain decorative gravel, and AZ Chocolate Patio Stone flagstone.

Can landscaping be added after the hardscape is already underway?

Yes. On this project, the first hardscape phase was followed by a return visit, scheduled with the homeowners, for planting, drip irrigation, Mission Mountain decorative gravel, and AZ Chocolate Patio Stone flagstone. That phased approach can work well when homeowners want the main hardscape locked in first and the landscape finish refined after seeing the space take shape.

Your Outdoor Project in 3 Simple Steps

1

Design

We listen to your vision, assess your space, and create a custom design that fits your lifestyle and budget.

2

Build

Our experienced crews bring the design to life with premium materials and expert craftsmanship.

3

Enjoy

Step into your transformed outdoor space and start making memories with family and friends.

Your Project Manager

Troy MacMillan

Troy MacMillan

A San Diego native with more than 20 years in landscape construction, Troy brings seasoned craftsmanship to every build. A devoted husband and father of two, he carries the same care from the job site to his weekend farm.

Ready to Transform Your Outdoor Space?

Let's discuss your project and bring your vision to life.