Paver terrace and curved seat wall below the pool deck, Poway 92064

Poway Paver Terrace with a Curved Seat Wall Below the Pool Deck

This finished project was a $54k-$58k build.

Project Snapshot

Location Poway (92064)
Style Resort
Timeline Apr 30 to May 27, 2025 · about 4 weeks
Price Range $54k-$58k

– Angelus Courtyard Combo (Standard) 60 mm pavers, 1,272 sq ft installed
– NextGel polymeric sand (tan) across the 1,272 sq ft of joints
– Angelus Stonewall II wall block, 145 sq ft of face built (195 sq ft billed)
– Angelus Stonewall II cap units, 130 ln ft
– Freestanding wall footing, 12 by 12 inch, 130 ln ft
– Country Manor step risers, 8 ln ft
– Pro-Trade 300 W stainless steel TR1 transformer, 1
– Pro-Trade LL2 7-inch ledge lights, bronze, LED, 15
– Pro-Trade PTH1 15-inch path lights, aluminum bronze, 2.5 W 2700 K LED, 6
– Smart socket timer, 1; 12/2 low-voltage wire, one 250 ft roll
– Source: the CIQ project sheet (job control sheet quantities), read November 17, 2026

– 3-inch SDR35 drain line, 90 ln ft
– 5 plastic drain caps and downspout connections
– Drain line set before the base; soil moved to the back planting area at the homeowner’s request
– 28 yards of soil hauled off site (job control sheet; 32 yards were billed)

– Contract signed April 24, 2025; demolition April 30 to May 1
– Pool plumbing and light wiring rerouted by the homeowner’s pool contractor, and the paver delivery on May 13; crew back May 20
– Drainage, footing, wall and lights May 20 to 22; steps and pavers May 23 to 27; final inspection checklist May 27
– Completion certificate and final payment May 31, 2025

– Three change orders (May 2, 27 and 29, 2025) removed the gas line and the barbecue island at the homeowner’s request and took the contract from $65.8K to $56.1K as built (CIQ record)
– The pool light’s copper conduit, a few inches under the old deck, was cut during demolition; the homeowner’s pool contractor rerouted the pool lines and replaced the light, and the cost of the light was in dispute at close-out
– The homeowner held part of the final payment until the punch list (gaps behind the wall block at the steps, loose pavers moved aside) was done

Project Story

Overview

A Poway homeowner turned the unfinished ground below an existing concrete pool deck into a 1,272 sq ft paver terrace: Angelus Courtyard Combo pavers, a curved Angelus Stonewall II seat wall on a 130 ln ft footing, paver steps up to the pool deck, 90 ln ft of drainage and 21 low-voltage lights. Demolition started April 30, 2025 and the final inspection was May 27. The contract was signed at $65.8K and closed at $56.1K after the homeowner removed the gas line and barbecue island from the scope during the build.

The Challenge

  • The ground below the existing pool deck was unfinished: about 28 yards of soil had to be cut away and 120 sq ft of old brick, tile and flagstone removed before anything could be built.
  • Irrigation lines ran shallow through the work area and the pool light's copper conduit sat a few inches under the old deck, so both had to be rerouted before the wall footing could go in.
  • The lower level had no lighting, so the steps between the terrace and the pool deck were dark after sunset.

What Changed

The lower level is now 1,272 sq ft of Angelus Courtyard Combo pavers held by a curved Stonewall II seat wall, with paver steps up to the existing pool deck, 90 ln ft of drainage under it and 21 low-voltage lights along the wall, the steps and the path. The gas line and barbecue island in the original contract were removed at the homeowner's request, so this is a seating and dining level rather than a cooking one.

How INSTALL-IT-DIRECT Helped

The homeowner had unfinished ground below an existing concrete pool deck. Install It Direct cut the grade, ran 90 ln ft of drainage, poured a 130 ln ft footing and built a curved Angelus Stonewall II seat wall with paver steps up to the pool deck, then laid 1,272 sq ft of Angelus Courtyard Combo pavers and wired 21 low-voltage lights on a timer. The gas line and barbecue island in the original contract were removed at the homeowner's request during the build, so the level is for sitting and dining. Demolition started April 30, 2025 and the final inspection was May 27.

Over 1,000 five-star reviews and 1,500+ San Diego homeowners served.

Paver terrace with a curved seat wall and steps up to the pool deck, Poway 92064

Design & Build

The Plan

  • 1,272 sq ft of Angelus Courtyard Combo 60 mm pavers on compacted road base and 1 inch of bedding sand, with a border where the terrace meets the existing concrete pool deck

  • A curved Angelus Stonewall II seat wall (145 sq ft of face as built) on 130 ln ft of 12 by 12 inch concrete footing, capped with 130 ln ft of Stonewall II caps cut to the curve

  • Paver steps up to the pool deck built with Country Manor step risers (8 ln ft), following the curve of the wall; the lower tread 2 inches wider than the upper, caps with a 1.5 inch reveal on the front and sides

  • 90 ln ft of 3-inch SDR35 drain line with 5 drain caps, set before the base went down

  • 15 Pro-Trade LL2 ledge lights in the wall face and steps, 6 Pro-Trade PTH1 path lights, a 300 W Pro-Trade transformer and a smart socket timer

  • A planter strip 2 ft 6 in off the house, curving to the corner where the terrace meets the existing concrete (the PM’s layout of May 22, 2025)

The Build

Demolition and soil removal (April 30 to May 1, 2025)

The crew set up with a portable restroom and a skid-steer, cut the slope below the pool deck and hauled the soil off in 12 and 20 yard containers; the job control sheet records 28 yards. Old brick, tile and flagstone (120 sq ft) went with it. The existing irrigation ran shallow and the skid-steer took some of it out, so new 3/4 inch PVC lines were run before anything was backfilled.

The pool conduit and a two-week pause (May 1 to 19)

During demolition the crew cut the copper conduit to the pool light, which sat a few inches under the old deck with its wire inside. The homeowner's pool contractor rerouted the 2-inch pool lines and the light wiring at a lower elevation, clear of the new wall and pavers. The Angelus pavers were delivered May 13 and the crew returned May 20.

Drainage, footing and wall (May 20 to 22)

90 ln ft of 3-inch SDR35 drain line and 5 caps went in, soil was moved to the back planting area at the homeowner's request, and the 130 ln ft footing was poured. The Stonewall II wall was stacked on its curve, the ledge lights were wired into the wall face and the steps, and the caps were cut to follow the curve along most of the run.

Steps and pavers (May 22 to 27)

The steps up to the pool deck were laid out on site: the lower tread 2 inches wider than the upper, the sides matching the wall, the caps with a 1.5 inch reveal on the front and the sides. Road base and 1 inch of bedding sand went down May 23, the Courtyard Combo pavers were laid May 23 to 27 with border cuts along the existing concrete, and polymeric sand was swept in. The final inspection checklist closed May 27.

Close-out

The gas line and the barbecue island were removed from the contract at the homeowner's request during the build; three change orders took the contract from $65.8K to $56.1K as built. The cost of the pool light replaced after the conduit was cut was in dispute at close-out, and the homeowner held part of the final payment until the punch list was done. The completion certificate and final payment closed on May 31, 2025.

Investment

What would a similar project cost in Poway?

Toggle components on/off to estimate your project

Pavers: 1,272 sq ft of Angelus Courtyard Combo 60 mm on compacted base and bedding sand, polymeric sand, delivery, backyard access $27,500 – $29,500
Curved seat wall, footing and steps: Angelus Stonewall II (145 sq ft of face as built), 130 ln ft of 12 by 12 inch footing, 130 ln ft of caps, 8 ln ft of step risers $15,000 – $16,000
Demolition and site work: excavation, 28 yards of soil hauled off, 120 sq ft of old brick, tile and flagstone removed, portable restroom $6,800 – $7,400
Low-voltage lighting: 15 ledge lights, 6 path lights, 300 W transformer, smart socket timer, wire $3,200 – $3,400
Drainage: 90 ln ft of 3-inch SDR35 drain line with 5 drain caps $1,500 – $1,700
Estimated Total

Frequently Asked Questions

How much does a paver patio with a seat wall cost in Poway?

$54K to $58K as built for this one. The contract was signed at $65.8K in April 2025, and three change orders during the build, which removed the gas line and the barbecue island at the homeowner's request, brought it to $56.1K as built (CIQ project record and project sheet). That covered 1,272 sq ft of Angelus Courtyard Combo pavers, the curved Stonewall II seat wall with its footing and caps, the steps, 90 ln ft of drainage, 21 low-voltage lights and the demolition. The wall, footing and steps were about 28 percent of the total.

Do Angelus Courtyard Combo pavers need much maintenance next to a pool?

No. They are individual interlocking units set in bedding sand with polymeric sand joints. If a unit cracks or a section settles, the pieces can be pulled and reset without replacing the whole terrace. Re-sanding the joints every few years keeps them tight, and pressure washing should not be aimed into the joints, which displaces the sand.

How long did this Poway paver terrace take to build?

Four weeks on the calendar, April 30 to May 27, 2025, with about two weeks of that waiting on the homeowner's pool contractor and the paver delivery. The crew's own work was demolition on April 30 and May 1, then drainage, footing, wall, steps and pavers from May 20 to 27.

What happens when a crew hits a pool conduit during demolition?

On this job the pool light's copper conduit sat a few inches under the old deck and was cut during demolition. The pool's lines and the light wiring were rerouted at a lower elevation by the homeowner's pool contractor before the footing went in, and the cost of the replacement light was disputed at close-out. Locating the pool's electrical and plumbing before demolition is the way to avoid it.

Your Outdoor Project in 3 Simple Steps

1

Design

We listen to your vision, assess your space, and create a custom design that fits your lifestyle and budget.

2

Build

Our experienced crews bring the design to life with premium materials and expert craftsmanship.

3

Enjoy

Step into your transformed outdoor space and start making memories with family and friends.

Your Project Manager

Patrick Diehl

Patrick Diehl

Born and raised in San Diego, Patrick has managed residential, commercial, and high-rise builds, with a specialty in hardscape. A licensed real-estate agent and certified home inspector, he's committed to delivering every project with quality, compliance, and on-time results.