Paver Driveway Extension with Paver Lights in Vista
This finished project was a $30k-$33k build.
Project Gallery
The palm island at the final walk on October 30: 32 linear feet of paver on edge set in concrete ring the bed, with the pavers running around it in two blends.
Where the pavers meet the old concrete: the mocha soldier course doubles as the border and the transition, and the 500 square feet of lawn that stood here came out to 4 inches.
The paver field on October 30: Angelus Courtyard Combo, 60 mm, in the sand, stone and mocha and adobe, copper and mocha blends the owners chose at the pre-walk.
Project Snapshot
Project Story
Overview
In Vista 92081 the crew took out 500 square feet of lawn beside the concrete driveway and laid 1,395 square feet of Angelus Courtyard pavers in sand, stone, mocha, adobe and copper blends with a solid mocha border, curving the new parking court around a palm island ringed in paver on edge, with six paver lights in the border and 25 feet of drain line under it. Demolition started October 21, 2024 and the final walk was October 30, two weeks on site. $30K to $33K as built.
The Challenge
- A concrete driveway with a lawn beside it and no room to park or turn a second car, and a mature palm in the middle of the space that was staying.
- The new surface had to meet the concrete on one side and the planting beds on the other with a clean edge, and the old lawn's sprinklers ran under it.
- The start slipped four days when the crew's demolition truck broke down, and the owners wanted the outer curve held to the line agreed at the pre-walk.
What Changed
How INSTALL-IT-DIRECT Helped
Over 1,000 five-star reviews and 1,500+ San Diego homeowners served.
Design & Build
The Plan
Pavers: 1,395 sq ft of Angelus Courtyard Combo, 60 mm, in two blends the owners chose at the pre-walk (sand, stone and mocha; adobe, copper and mocha) with a solid mocha soldier border, laid as a parking court beside the existing concrete driveway.
Palm island: the mature palm stayed; 32 ln ft of paver on edge set in concrete ring its bed and the pavers curve around it; the path lights on the island are the owners’ and are not in this price.
Edge: the outer curve follows the line walked at the pre-walk on October 14, and the mocha border runs along the concrete so the two surfaces meet in one straight course.
Lighting: six Pro-Trade SL1 4.5-inch surface-mounted LED lights set into the paver border along the curved edge; no transformer in the contract, so they run off the lighting already on the property.
Drainage and irrigation: 25 ln ft of 3-inch SDR35 drain line with three drain caps or downspout connections under the new pavers; the old lawn’s sprinkler heads at the edge moved or capped so they no longer spray the driveway.
Demolition: 500 sq ft of lawn and soil removed to 4 inches outside the paver area, roots and 2.5 loads of soil hauled, five crew hours of demolition labor.
The Build
Pre-walk and start (October 14 to 21)
The pre-walk was October 14, 2024, after the owners chose the two paver blends and the mocha border with the designer on October 11. The schedule called for demolition on October 18, but the crew's demolition truck broke down, so the dumpster and the first pallets arrived October 21 and demolition started that day with the first progress payment collected. The owners kept the right side of their driveway for their cars throughout.
Demolition, base and pavers (October 21 to 28)
The lawn and soil came out to 4 inches over the first two days and the demolition checklist (roots, cuts, debris, safety gear) was closed October 22. Angelus delivered the pavers in two truck loads from October 23, the day the drainage and irrigation parts went on site and the owners asked that the outer curve follow the pre-walk line; the curve was set to it October 24. The paver lights and cable went in with the border on October 24 and 25, the second progress payment was collected October 25, and the field was finished over the weekend. The office's note of October 28: the clients love their new driveway extension, and the PM suggested it for a photo shoot.
Punch list and close-out (October 28 to 31)
The punch list of October 28 had three items: the plastic off the new lights, the sprinkler nozzles turned away from the driveway, and the valves that fed the old lawn capped. At the final walk on October 30 the certificate of completion was signed and the final payment collected; the PM's note was that the clients love the driveway, especially lit at night, and the office's note that the owner was very pleased with how thorough the job felt and would submit reviews. One deductive change order of $550 closed the contract at $30.5K and CIQ marked the job complete October 31, 2024.
Investment
What would a similar project cost in Vista?
Toggle components on/off to estimate your project
Frequently Asked Questions
What did this project cost?
$30K to $33K. The contract was signed at $31.0K in October 2024 and one deductive change order at close-out took $550 off, so the total as built was $30.5K. The table above groups the 14 lines of the project sheet into four rows; each row holds the sheet figure and the figure scaled to the total, which is why the rows add up to the range shown. Quantities on this page are what the crew logged as installed; where the sheet billed more material (1,456 sq ft of pavers for 1,395 laid, 58 ft of drain line for 25), both figures are given.
Where does the water go?
Into 25 linear feet of 3-inch SDR35 drain line under the new pavers with three drain caps or downspout connections. The old lawn's sprinkler heads at the edge were moved or capped on the punch list so they no longer spray the driveway.
What pavers are these?
Angelus Courtyard Combo pavers, 60 mm thick, in two blends the owners chose with the designer on October 11, 2024: sand, stone and mocha for one and adobe, copper and mocha for the other, with a solid mocha soldier border. 1,395 square feet were laid from 1,456 supplied.
How long did it take?
Two weeks on site. Demolition started October 21, 2024 (four days later than planned, after the crew's demolition truck broke down), the pavers arrived October 23, the lights and border went in October 24 and 25, the punch list was October 28 and the final walk October 30.
What are the lights in the border?
Six Pro-Trade SL1 4.5-inch surface-mounted LED lights set into the paver border along the curved edge, which is what shows in the night photo. The path lights on the palm island and the up lights in the beds were the owners' and are not in this price.
Did the palm stay?
Yes. The pavers curve around it, and 32 linear feet of paver on edge set in concrete ring its bed so the pavers hold a clean line against the soil.
Your Outdoor Project in 3 Simple Steps
Design
We listen to your vision, assess your space, and create a custom design that fits your lifestyle and budget.
Build
Our experienced crews bring the design to life with premium materials and expert craftsmanship.
Enjoy
Step into your transformed outdoor space and start making memories with family and friends.
Ready to Transform Your Outdoor Space?
Let's discuss your project and bring your vision to life.